CEB Press IV
  • Finally the drawings for the CEB Press Version IV are released.
    Its one of the oldest OSE developments, and to my knowledge a working one.


    Looking at the drawings I find a lot of issues to discuss. OSE with its goals for industrial efficiency should be up to industrial efficiency also in its designs and documentation, the technical drawings.


    Some poor examples now:


     Page 4: A pin - a very simple basic part, nearly not worth doing a drawing.

    image
     
    Attachments
    4Fehler.JPG 107K
  • 7 Comments sorted by
  • Lets see page 37. An angle


    Its confusing to omitt hidden lines. The dimensioning could be improved, a centerline inserted.
    The hole through the inner radius of that angle looks like a design error. You can't install a nut there, on a curved surface

     
    Attachments
    37Fehler.jpg 205K
  • Lets look at a threaded rod, shown on page 24.


    How, threaded???


    I don't see any thread. No symbol for a thread drawn. No dimensions for a thread. The round part has a dimension of Ø3/4" - that's not thread.


    Its also questionable if it's necessary to make a drawing for a standard threaded rod available in any hardware store. And if the thread isn't standard, it definitely needs to be clearly specified in the drawing.

     
    Attachments
    24Fehler.jpg 134K
  • See a top view of a sheet steel part on page 43


    It's just ugly to place the dimensions this way.
    Worse, its a mistake to use such a corner as base for dimensions, they always have a radius from cutting. You cannot do proper layout lines from this corner, nor can a machinist with an DRO/CNC equipped machine exactly indicate his display at that corner.


    For manual cutting I would also dimension the angles in brackets.


     

     
    Attachments
    43Fehler.jpg 228K
  • Similar part with similar problems on page 42


    Here one dimension is misleading, and 2 others are missing completely.....


    IMO it would be helpful to install for OSE to implement some quality control for drawings.
    In industry most drawings are made by highly skilled professionals who make drawings all day long. Nevertheless its standard in most companies that every drawing is checked for errors by a second engineer or technician before it is released for production.

     
    Attachments
    42Fehler.jpg 207K
  • I started drafting when lead on vellum and slide rules where the norm. A considerable amount of work was needed to create drawings, so the quality of the work was taken seriously. Also, vendors and lawyers could try to take advantage of any flaw or ambiguity when a dispute came up. On the other hand, the drafter created these drawings from rough sketches, verbal instructions and hand waving. One might consider these CEB drawings as sketches, and as Bastelmike mentions, it would be better to have a review system to develop and review these before they can be presented as official.

    Maybe for the short term, a link could be added here:
    http://opensourceecology.org/wiki/Civilization_Starter_Kit_DVD_v0.01#CEB_Press

    such as "CEB Drawings, Preliminary", then move the drawings over to a link with higher status as they are developed. Unfortunately, the drawings aren't even signed, so one would not know where to go if one where inclined to help.

    If anyone from the development team reads this, please reply so that we at the wiki know there is some sort of connection between the wiki and the inner circle.

    --
    Kirk Wallace
    http://www.wallacecompany.com/machine_shop/
    http://www.wallacecompany.com/E45/index.html
    California, USA
     
  • Yeah, you just cannot make perfect fab drawings from a virtual model straight up like this. You always forget things that you correct while it's being fabricated. The first fabrications of a machine should be in collaboration with the draftsman to fix simple errors like mentioned above. I would also suggest first fabrications of a newly designed machine should fill out a type of work procedure sheet as a guide for future fabrications which could be included in the fab dwgs or maybe hosted on the wiki. I would defs use the revision feature of the cad software when making changes or it could get mighty confusing in a team environment. I offered my CAD time to Marshall a couple of months ago for this project however I know Inventor proficiently while this design was started in Solidworks. If down the track the dwgs are not progressing then I could work on some after converting to Inventor as I need some experience in this area of CAD.

    p.s. Metric should be released along side imperial. Inventor can switch between the two with a press of a button when printing. I would say Solidworks can do this too. If I had any say about it Metric should be the standard for all OSE projects. It's time you guys in the states lifted the bar a bit and stop using this ancient measuring system. The time factor alone should be enough reason.
     
  • I would prefer that the open software listed here should be used:
    http://opensourceecology.org/wiki/OSE_Linux_Build

    That way there is a path for more of us (Liinux/open source only) to get involved. To me the equipment development should focus on getting an open development system established rather than the equipment development itself.

    I see no problem for anyone that cares, to redraw the the current CEB drawings:
    http://opensourceecology.org/w/images/5/51/OSE_-_Fabrication_Drawings_-_CEB.pdf

    preferably using the OSE distribution software and preferably with collaboration with the CEB developers. The new drawings could be posted to one of the free file repositories and  announced and linked here. If enough people were involved, each person could do one drawing and check one other person's drawing, making for light work.

    In reference to revisions, this has been an issue for at least a few hundred years and should be pretty well understood. It's just a matter of finding an example system and incorporating it.

    As for using the Metric system, I'm all for making it the OSE standard. It's just a matter of the the powers that be and the rest of us to put in the effort to stick to it, which has been the case ever since the Metric system was introduced to the U.S.
    --
    Kirk Wallace
    http://www.wallacecompany.com/machine_shop/
    http://www.wallacecompany.com/E45/index.html
    California, USA
     

Howdy, Stranger!

It looks like you're new here. If you want to get involved, click one of these buttons!

Login with Facebook Sign In with Google Sign In with OpenID Sign In with Twitter

In this Discussion

Loading